N
nzeches
Hello folks
I have a project with tenths of items to ship to a site before work
can start.
I currently maintain a list of milestones with suppliers deliveries
(EXW), however I have to add to the delivery date the time for
shipment, which is a constant for my project.
There are several ways to do it, eg for 35 days of transport:
- either I add one 35 days "transport" task (although this is not a
task of my project) as a successor to each delivery milestone (~70
tasks) with a successor milestone "item X available on site"
- or I create a successor milestone to each delivery with a "FS
+35days" link for the final delivery to site
Let us consider that transport is now 55days ; I have to update
manually ~70 tasks scattered across my 500+ ytasks project to reflect
the change (hoping not to miss one).
How could I create a "constant" called "shipment time" which I could
use in each task duration or link, that I could easily change once and
for all ?
Thanks in advance for your advice
I have a project with tenths of items to ship to a site before work
can start.
I currently maintain a list of milestones with suppliers deliveries
(EXW), however I have to add to the delivery date the time for
shipment, which is a constant for my project.
There are several ways to do it, eg for 35 days of transport:
- either I add one 35 days "transport" task (although this is not a
task of my project) as a successor to each delivery milestone (~70
tasks) with a successor milestone "item X available on site"
- or I create a successor milestone to each delivery with a "FS
+35days" link for the final delivery to site
Let us consider that transport is now 55days ; I have to update
manually ~70 tasks scattered across my 500+ ytasks project to reflect
the change (hoping not to miss one).
How could I create a "constant" called "shipment time" which I could
use in each task duration or link, that I could easily change once and
for all ?
Thanks in advance for your advice