C
Cecile
I am using a constraint 'as late as possible' for one task amont many tasks
having a constraint 'as soon as possible'. It delays my project end date when
I just wanted it to delay one task! I can't easily explain, but here is an
example:
Iteration 1 contains:
- Task 1a
- Task 1b
- Deadline 1
Iteration 2 contains
- Preparation 2
- Task 2
Iteration 3 contains:
- Preparation 3
- Task 3
Task 2 depends on Task 1a and Task 3 on task 1b. All I am trying to do is
have Preparation 2 finishing just before Task 2 and Preparation 3 finishing
just before Task 3.
When I use an ALAP constraint on Preparation 2 and 3, task 2 is delayed to
end at the same time as task 3, which is NOT what I want...
Thanks for your help!
having a constraint 'as soon as possible'. It delays my project end date when
I just wanted it to delay one task! I can't easily explain, but here is an
example:
Iteration 1 contains:
- Task 1a
- Task 1b
- Deadline 1
Iteration 2 contains
- Preparation 2
- Task 2
Iteration 3 contains:
- Preparation 3
- Task 3
Task 2 depends on Task 1a and Task 3 on task 1b. All I am trying to do is
have Preparation 2 finishing just before Task 2 and Preparation 3 finishing
just before Task 3.
When I use an ALAP constraint on Preparation 2 and 3, task 2 is delayed to
end at the same time as task 3, which is NOT what I want...
Thanks for your help!