J
Jay
I created a project plan, but did not use constraints. All tasks have the
constraint icon, with the properties "start no earlier than". Don't need
them, however, when I change to ASAP, it takes the start date for all tasks
and uses the project start date. I don't want that....I want dates ranging
from Jan 1 - Oct. 21. With that, my project start is Jan 1 and end is Oct.
21. Nothing is outside of that range.
How do I rid of the constraints, but maintain the individual task start dates?
Thanks
Jay
constraint icon, with the properties "start no earlier than". Don't need
them, however, when I change to ASAP, it takes the start date for all tasks
and uses the project start date. I don't want that....I want dates ranging
from Jan 1 - Oct. 21. With that, my project start is Jan 1 and end is Oct.
21. Nothing is outside of that range.
How do I rid of the constraints, but maintain the individual task start dates?
Thanks
Jay