K
kimmerj
I am trying to manage several active projects (none of them with too many
milestones) from within one project file. Each parent task represents a
separate project.
I have created 3 custom fields:
Date1 - Estimated Start
Date2 - Estimated Finish
Duration1 - Estimated Duration - [Date2] - [Date1]
Text1 - Estimated Duration - using DateDiff in the formula
I would like these fields to behave (have the same relationship with each
other in regard to dependencies, formulas, predecessors, etc) as the "start",
"finish" and "duration" fields. I have 2 issues:
1. I cannot get either the custom duration field to calculate the duration
using the custom date field. Not sure what the formula for that field should
be. In trying to use a text field with the DateDiff function, I am not able
to exclude weekends in the duration calculation.
2. I cannot get the dates to behave like the other date fields in regard to
the predecessor.
I am intending to use them to take a snapshot of the original estimates and
then to be able to track variance between orignal estimates and actual dates.
I know that this may not be the best way to accomplish this and am open to
alternate suggestion.
milestones) from within one project file. Each parent task represents a
separate project.
I have created 3 custom fields:
Date1 - Estimated Start
Date2 - Estimated Finish
Duration1 - Estimated Duration - [Date2] - [Date1]
Text1 - Estimated Duration - using DateDiff in the formula
I would like these fields to behave (have the same relationship with each
other in regard to dependencies, formulas, predecessors, etc) as the "start",
"finish" and "duration" fields. I have 2 issues:
1. I cannot get either the custom duration field to calculate the duration
using the custom date field. Not sure what the formula for that field should
be. In trying to use a text field with the DateDiff function, I am not able
to exclude weekends in the duration calculation.
2. I cannot get the dates to behave like the other date fields in regard to
the predecessor.
I am intending to use them to take a snapshot of the original estimates and
then to be able to track variance between orignal estimates and actual dates.
I know that this may not be the best way to accomplish this and am open to
alternate suggestion.