J
Jeu
I have a problem with tracking different cost types and reporting on them
(EPM 2007)
The requirement: I have different cost types. e.g a. external costs, b.
Business resource cost, c. IT resource cost, and need to produce executive
project center dashboard views that will show all projects in a portfolio
together with the cost break down at project level. i.e I need columns
showing me the cost types as header and holding the sums at project level.
My attempt: I have created custom enterprise task-level cost fields (rollup:
sum) to hold the different cost types and custom enterprise project-level
cost fields (formula= custom task-level cost) to keep the sum respectively. I
am able to meet the reporting requirements with this approach.
My concern: Task Actual Costs are not populated, thus all out of the box
project server health reports become useless. I also lose all the benefit of
cost baselines, cost variances etc...
Is there a way of having my task Actual Cost take the sum of my different
custom cost types, so that everything out of the box works as they should and
I also meet my reporting requirements?
Please suggest other possible approach, if any. Thanks.
(EPM 2007)
The requirement: I have different cost types. e.g a. external costs, b.
Business resource cost, c. IT resource cost, and need to produce executive
project center dashboard views that will show all projects in a portfolio
together with the cost break down at project level. i.e I need columns
showing me the cost types as header and holding the sums at project level.
My attempt: I have created custom enterprise task-level cost fields (rollup:
sum) to hold the different cost types and custom enterprise project-level
cost fields (formula= custom task-level cost) to keep the sum respectively. I
am able to meet the reporting requirements with this approach.
My concern: Task Actual Costs are not populated, thus all out of the box
project server health reports become useless. I also lose all the benefit of
cost baselines, cost variances etc...
Is there a way of having my task Actual Cost take the sum of my different
custom cost types, so that everything out of the box works as they should and
I also meet my reporting requirements?
Please suggest other possible approach, if any. Thanks.