S
Scrufnut
I'm using Project 2003 and have used "edays" many times before with no
problems. I am having to make adjustments to a project schedule a co-worker
created and I noticed where he used "edays" in a task predecessor, the head
task rolled up with a fractional number of days. All of the tasks below the
heading are whole numbers and all of the predecessors are whole numbers. I
can not figure out why the heading task rolls up to a fractional number of
days. Any ideas?
problems. I am having to make adjustments to a project schedule a co-worker
created and I noticed where he used "edays" in a task predecessor, the head
task rolled up with a fractional number of days. All of the tasks below the
heading are whole numbers and all of the predecessors are whole numbers. I
can not figure out why the heading task rolls up to a fractional number of
days. Any ideas?