Using Graphical Indicators in Tasks but showing Values in Summary

C

Christina

I created several custom number fields that I would like to see a graphical
indicator (i.e. check mark) in the nonsummary task rows but would like to
have the average values appear on the summary rows.
The values are there but they are not visible.

How can I get the numerical values to be visible at the same time the
graphical indicators are shown for the non summary rows?

Any suggestions are greatly appreciated.
 
J

JulieS

Hello Christina,

To the best of my knowledge, I don't believe that is possible. You can
modify the graphical indicators (including criteria) for summary rows,
but I don't believe you can show graphical indicators for some and
values for another. It is either all graphical or all values.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 