Hi all, I hope someone can help me with this issue.

When I import a work-item with a Start and Finish date from Team Foundation
Server (TFS) to a project, I dont get the correct dates from TFS in Project.
I have tried to change between the Default task types in Project. I get the
correct Start date using the task type Fixed duration and will get the
correct Finish date when I refresh after importing the work item.

Do anyone know how I can get the correct dates without refreshing after
importing?

Thanks
Sølvi
 
G

glenATmvps.org

Hi Salvi,

You might get a better response from the server newsgroup. Try posting
on the microsoft.public.project.server newsgroup (forum). Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm

Mike Glen
Project MVP
 