Hi all, I hope someone can help me with this issue.
When I import a work-item with a Start and Finish date from Team Foundation
Server (TFS) to a project, I dont get the correct dates from TFS in Project.
I have tried to change between the Default task types in Project. I get the
correct Start date using the task type Fixed duration and will get the
correct Finish date when I refresh after importing the work item.
Do anyone know how I can get the correct dates without refreshing after
importing?
Thanks
Sølvi
When I import a work-item with a Start and Finish date from Team Foundation
Server (TFS) to a project, I dont get the correct dates from TFS in Project.
I have tried to change between the Default task types in Project. I get the
correct Start date using the task type Fixed duration and will get the
correct Finish date when I refresh after importing the work item.
Do anyone know how I can get the correct dates without refreshing after
importing?
Thanks
Sølvi