S
Sebastián Armas
I'm planning on using MS Project Server 2007 to consolidate very simple data
from projects: task duration, % completed, human resources allocated, hrs
allocated per task.
I'm going to define the projects and their attributes (to be used for
reporting and analysis) directly through Project Server 200, and I'm planning
to update the task/resources data via MSP files.
The catch, as you might have guessed, is that all of the Project Managers
use MSP 2002 and upgrading to MSP Pro 2007 is moot (licensing and approval
upgrade cycle are just out of the question).
I'm not thinking on posting from MSP 2002 to the server; rather, I'm trying
to find out if it's feasible to upgrade the (server) projects' task/resources
data using the MSP 2002 files... and ideally keeping the projects previously
defined attributes.
Thanks in advance for your kind reply.
from projects: task duration, % completed, human resources allocated, hrs
allocated per task.
I'm going to define the projects and their attributes (to be used for
reporting and analysis) directly through Project Server 200, and I'm planning
to update the task/resources data via MSP files.
The catch, as you might have guessed, is that all of the Project Managers
use MSP 2002 and upgrading to MSP Pro 2007 is moot (licensing and approval
upgrade cycle are just out of the question).
I'm not thinking on posting from MSP 2002 to the server; rather, I'm trying
to find out if it's feasible to upgrade the (server) projects' task/resources
data using the MSP 2002 files... and ideally keeping the projects previously
defined attributes.
Thanks in advance for your kind reply.