say i have 3 columns <ID> <Est Finish Date> and <Actual Finish Date> and I
want an extra column that tells me how many working days before or after the
estimated finish date the actual finish date is. I used Networkdays and it
gave me the number of days after the estimated date minus the weekends,
however when the actual date was before the estimated date the formula still
counted the weekends.
Does anyone know a way of stopping this from happening?