R
rockcandy2006
I am using MS Project 2007. I like the GANTT chart scheduling sectio
but most of my tasks have lot of notes that i take down durin
scheduling meetings and i like to put them under Notes column so other
can see the history when they print it out. But the problem is if I ad
a custom Notes column it only shows the first line of notes if I hav
multiple lines in one note. Has anyone come across this and found a wa
to overcome it?
Thank
but most of my tasks have lot of notes that i take down durin
scheduling meetings and i like to put them under Notes column so other
can see the history when they print it out. But the problem is if I ad
a custom Notes column it only shows the first line of notes if I hav
multiple lines in one note. Has anyone come across this and found a wa
to overcome it?