How do I use Percent Work Complete to update finish dates or otherwise
highlight when a task is behind schedule? For instance if a task will take
40hrs and the percent work complete is 10% and the task is due to tomorrow,
how do I highlight that and or update the finish date to reflect the current
burn/completion rate? I am looking for a discrete measure to know whether or
not we are on target. I am also looking for a quick way to adjust completion
dates when necessary.
BTW. I am a novice user who finds Project rather mystifying.