Using PERT Analysis in MS Project 2000

S

Sumit Taneja

Hi
I'm trying to use the PERT Analysis features in MS Project 2000 and am
having a problem. I'm in the Gantt chart view, and have the PERT Analysis
toolbar displayed. I have some tasks for which I want to enter optimistic,
pessimistict and expected durations. Nothing happens when I click on any of
the buttons on this toolbar - including PERT Entry Form and PERT Entry Sheet.
Does anyone know what is going on?
 
D

davegb

Not sure on this one. You might try re-installing Project. I think
these are VBA macros. If so, maybe something wrong that way
 
M

Mike Glen

Hi Sumit,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 46. Analysis Toolbar (Project 2000+)

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question