Hello - I want to use the Physical % Complete column to calculate EVM because
it is a better gauge of task completion. It is also the only field that I've
found that doesn't automatically calculate the actual cost based on time.
I enter resource hours on a daily basis to track actual costs. Any
suggestions on how to keep % progress independent from the actual hours I
enter and still show a summary level progress? Even if all my subtasks are
100% complete the main task remain 0% and I cannot even manually enter it.
Thanks, Leena