rebecca
What is the best practice for combining the project that's created
when you export a project from Portfolio Server with an MSP pro
enterprise project template?
I have heard the best way to integrate these is to copy the tasks from
the MSP pro template into the project that was exported from Portfolio
Server.
However, the exported project doesn't use the Enterprise Global
project settings so this process produces a bunch of errors.
(mismatched duration settings, "h" v "hrs").
Plus, this is just not a very pretty solution.
Any hints?
Thanks!
when you export a project from Portfolio Server with an MSP pro
enterprise project template?
I have heard the best way to integrate these is to copy the tasks from
the MSP pro template into the project that was exported from Portfolio
Server.
However, the exported project doesn't use the Enterprise Global
project settings so this process produces a bunch of errors.
(mismatched duration settings, "h" v "hrs").
Plus, this is just not a very pretty solution.
Any hints?
Thanks!