P
PJR
I'm involved in a software project where to prevent Resource Over Allocation
multiple Predecessor Task relationships have been setup based upon Resource
Assignment. I've communicated to the Program Manager that Resource Leveling
should be used to prevent Over Allocation of Resources. The major drawback
I've tried to communicate is; the Critical Path based upon functionality of
the system (i.e. different screen designs, database table design) can't be
shown. Currently the Critical Path will show an individual name across many
of the different desired (but often un-related) functionality of the software.
Any ideas on how to communicate why using the Resource Leveling feature is
preferred over setting up Predecessor Tasks based upon Resource Assignment?
Note: Normal work stream to bring about software functionality is Business
Group will describe how something should look or work. Business Analyst from
IT will capture information and provide it to the developers to write the
code. Once the code is written then it will go through testing. Normally I
would expect a work stream or several work stream dependant upon each other
to be the critical path, not the same resource working on un-related work
streams (functionality) to show up as the critical path.
multiple Predecessor Task relationships have been setup based upon Resource
Assignment. I've communicated to the Program Manager that Resource Leveling
should be used to prevent Over Allocation of Resources. The major drawback
I've tried to communicate is; the Critical Path based upon functionality of
the system (i.e. different screen designs, database table design) can't be
shown. Currently the Critical Path will show an individual name across many
of the different desired (but often un-related) functionality of the software.
Any ideas on how to communicate why using the Resource Leveling feature is
preferred over setting up Predecessor Tasks based upon Resource Assignment?
Note: Normal work stream to bring about software functionality is Business
Group will describe how something should look or work. Business Analyst from
IT will capture information and provide it to the developers to write the
code. Once the code is written then it will go through testing. Normally I
would expect a work stream or several work stream dependant upon each other
to be the critical path, not the same resource working on un-related work
streams (functionality) to show up as the critical path.