P
Paul Filkin
Hello,
I have a project with hundreds of small tasks to be completed. I have
estimated durations for each one, but no real logic behind them. I wanted to
use MSProject to record progress and continually recalculate the time left.
So, I assigned Priorities to each items so that the general sequence of work
would be pretty realistic at least.
My problem is that the levelling priorities do not seem to be taken into
account at all and the sequence of work makes no sense to me.
I am sure I did this in the past with MSProject 2003, and now I have 2007.
Can you help point me in the right direction for anything I may have done
wrong.
Kind regards
Paul.
I have a project with hundreds of small tasks to be completed. I have
estimated durations for each one, but no real logic behind them. I wanted to
use MSProject to record progress and continually recalculate the time left.
So, I assigned Priorities to each items so that the general sequence of work
would be pretty realistic at least.
My problem is that the levelling priorities do not seem to be taken into
account at all and the sequence of work makes no sense to me.
I am sure I did this in the past with MSProject 2003, and now I have 2007.
Can you help point me in the right direction for anything I may have done
wrong.
Kind regards
Paul.