J
jtpryan
In the early stages of a project I wanted to use Project as sort of an
initial planning aid and outline things I wanted to do. So, I wanted
to do something like:
Task1
do this
do this
do this
Task 2
do this
do this
do this
Then mark Task 1 and Task 2 as milestones with the underlying things
under each as stuff that needs to get done to meet this milestone.
OK, so I have 2 problems. First, even though I mark the Task x lines
as milestones, they never pick up the font and color of milestones I
have defined if they have the "stuff to do" items listed below.
Second, lets say I expect Task x to take a day and in that day I want
to do the things listed below, well if I put 1 day next to each item
it appears that each one will take a day by itself and that doing 3 as
above will take 3 days.
I can't seem to find a logical way to do this, and obviously I am very
new to Project so maybe I'm using the wrong tool for the job, but it
seems as though I should be able to accomplish this.
Thanks in advance for any help.
Jim
initial planning aid and outline things I wanted to do. So, I wanted
to do something like:
Task1
do this
do this
do this
Task 2
do this
do this
do this
Then mark Task 1 and Task 2 as milestones with the underlying things
under each as stuff that needs to get done to meet this milestone.
OK, so I have 2 problems. First, even though I mark the Task x lines
as milestones, they never pick up the font and color of milestones I
have defined if they have the "stuff to do" items listed below.
Second, lets say I expect Task x to take a day and in that day I want
to do the things listed below, well if I put 1 day next to each item
it appears that each one will take a day by itself and that doing 3 as
above will take 3 days.
I can't seem to find a logical way to do this, and obviously I am very
new to Project so maybe I'm using the wrong tool for the job, but it
seems as though I should be able to accomplish this.
Thanks in advance for any help.
Jim