I've been experimenting with using resource pools, and am having some problems.

I've got a database set up with some plans already there, and a resource pool. I've been trying to import an existing plan, and attach it to the pool, but when I do so I find that task durations change (generally getting shorter)

I identified that this was partially down to different standard calendar definitions between the two files - the resource pool had a 7.5 hour day, and the plan had an 8 hour day. But having fixed that, the problem still happens

Anybody have any other suggestions as to why the task durations change?

Thanks
Roger
 
J

Jan De Messemaeker

Hi Ginster,

It's the resources' calendars that change the durations, not th "hour per
day" parameter.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Ginster said:
Hi,

I've been experimenting with using resource pools, and am having some problems.

I've got a database set up with some plans already there, and a resource
pool. I've been trying to import an existing plan, and attach it to the
pool, but when I do so I find that task durations change (generally getting
shorter)
I identified that this was partially down to different standard calendar
definitions between the two files - the resource pool had a 7.5 hour day,
and the plan had an 8 hour day. But having fixed that, the problem still
happens
 