uott2know
I have a project manager that would like to use this feature to enter
time for resources that are not going to report time through PWA.
However, he is unable to edit any of the information for the resources
he selected, which are on his project.
The server is set with the following:
Hours of work done per day or per week: Resources report the hours
worked on each task during each time period.
Allow project managers to change the default method for reporting
progress if a different method is appropriate for a specific project.
Non-managed periods
We do let the PMs choose the time reporting method for their project,
and in this case the project is using % complete to manage the
project.
I think I may have read that you can't use the Adjust Actuals function
with the % complete option, but I wasn't sure if that was at the
server or the project level.
Any insight on this would be great!!
Eric
time for resources that are not going to report time through PWA.
However, he is unable to edit any of the information for the resources
he selected, which are on his project.
The server is set with the following:
Hours of work done per day or per week: Resources report the hours
worked on each task during each time period.
Allow project managers to change the default method for reporting
progress if a different method is appropriate for a specific project.
Non-managed periods
We do let the PMs choose the time reporting method for their project,
and in this case the project is using % complete to manage the
project.
I think I may have read that you can't use the Adjust Actuals function
with the % complete option, but I wasn't sure if that was at the
server or the project level.
Any insight on this would be great!!
Eric