A
anand_am01
Hello,
This is a concundrum that has vexed me for some time now ... particularly in
the context of large projects (several '000 tasks & '00s of stakeholders)
Note: In the following discussion, I use the notation T1 ... Tn for Tasks;
and R1 ... Rn for Resources
Question:
What must be done to MS-Project (particularly on large projects ... with
several '000 of tasks) so that each relevant task (T1 ... Tn) can be assigned
to multiple resources (R1 ... Rn), with different RACI assignments in order
to achieve the following end results ...
What are the desired end-result(s)?
.... To be able to extract an ongoing report from MS-Project to answer the
questions:
A) What tasks is this resource (say R1 ... Rn) Responsible for, Accountable
for, Consulted in or Informed of?
B) Let's assume (quite realistically) that the Resource's level of
involvement in a task is different if he/ she is Responsible (e.g. 100%
involvement) vs. being Accountable (e.g. 40% involvement on Task 1, 50%
involvement on Task 2 etc etc ...
The question to be answered is ...
"How much time does the project require from this resource, overall?
Of that time, how much time will be required for Accountable, Responsible,
Consulted & Informed roles?"
I'm looking for steps & assignment that'll allow MS-Project to provide a
report such as,
"Resource R1 is Accountable for Tasks t1, t3, t5, t19 and t33; and this
requires
(say) 18 days.
Resource R1 is also Responsible for tasks t2, t6, t11-t16, t24-29; and this
requires (say) 90 days.
Resource R1 is also Consulted for tasks t4, t7, t17, t30; and this requires
(say) 5 days.
All told, the project requires 18 + 90 + 5 days of Resource R1's time."
Thanks for your responses,
/am
This is a concundrum that has vexed me for some time now ... particularly in
the context of large projects (several '000 tasks & '00s of stakeholders)
Note: In the following discussion, I use the notation T1 ... Tn for Tasks;
and R1 ... Rn for Resources
Question:
What must be done to MS-Project (particularly on large projects ... with
several '000 of tasks) so that each relevant task (T1 ... Tn) can be assigned
to multiple resources (R1 ... Rn), with different RACI assignments in order
to achieve the following end results ...
What are the desired end-result(s)?
.... To be able to extract an ongoing report from MS-Project to answer the
questions:
A) What tasks is this resource (say R1 ... Rn) Responsible for, Accountable
for, Consulted in or Informed of?
B) Let's assume (quite realistically) that the Resource's level of
involvement in a task is different if he/ she is Responsible (e.g. 100%
involvement) vs. being Accountable (e.g. 40% involvement on Task 1, 50%
involvement on Task 2 etc etc ...
The question to be answered is ...
"How much time does the project require from this resource, overall?
Of that time, how much time will be required for Accountable, Responsible,
Consulted & Informed roles?"
I'm looking for steps & assignment that'll allow MS-Project to provide a
report such as,
"Resource R1 is Accountable for Tasks t1, t3, t5, t19 and t33; and this
requires
(say) 18 days.
Resource R1 is also Responsible for tasks t2, t6, t11-t16, t24-29; and this
requires (say) 90 days.
Resource R1 is also Consulted for tasks t4, t7, t17, t30; and this requires
(say) 5 days.
All told, the project requires 18 + 90 + 5 days of Resource R1's time."
Thanks for your responses,
/am