T
Tim G
How should resources be handled if you want to assign a person resource to a
task as well as an equipment resource to the same task. For example. Task 5
has 8 person hours of work to be done as well as needing to allocate a tank
resource to be available. The person is working on the tank per say. It
would seem that allocating both resources to the task would cause durations
to calculate incorrectly.
What would be the correct configuration of task type and resource type and
how should this be managed
Thanks
task as well as an equipment resource to the same task. For example. Task 5
has 8 person hours of work to be done as well as needing to allocate a tank
resource to be available. The person is working on the tank per say. It
would seem that allocating both resources to the task would cause durations
to calculate incorrectly.
What would be the correct configuration of task type and resource type and
how should this be managed
Thanks