Hello;
I searched for similar posts here but no luck.
I am trying to assign variable resource usage rate to one task.
For example -
Task name : Pouring Concrete
Resource: m^3 of concrete
Rate: 20m^3 per day for first two days, 35m^3 for the next 3 days.
Is there a way to do it without splitting the task? Maybe something with
VBA? It would be great to have Project use resource usage driven tasks (i.e.
pour the concrete at the rate of 2m^3 per hour and see how long it takes to
finish it).
Thanks in advance for your answers,
Peja
I searched for similar posts here but no luck.
I am trying to assign variable resource usage rate to one task.
For example -
Task name : Pouring Concrete
Resource: m^3 of concrete
Rate: 20m^3 per day for first two days, 35m^3 for the next 3 days.
Is there a way to do it without splitting the task? Maybe something with
VBA? It would be great to have Project use resource usage driven tasks (i.e.
pour the concrete at the rate of 2m^3 per hour and see how long it takes to
finish it).
Thanks in advance for your answers,
Peja