Hello,
I'm trying to get my head round the workday and network day functions
and can't quite figure it out... I need to obtain the date on which a
task must start given that it must be finished by a known date and
given the number of WORKING days it is planned to take (Mon - Fri, no
holidays).
e.g.
Need Date: 15-August-2003
Project Days: 7
Required Start Date: 06-August-2003
(i.e project starts 6th August and is finished by the end of the day
on the 14th)
How can I do this?
TIA,
Dave Ferguson
I'm trying to get my head round the workday and network day functions
and can't quite figure it out... I need to obtain the date on which a
task must start given that it must be finished by a known date and
given the number of WORKING days it is planned to take (Mon - Fri, no
holidays).
e.g.
Need Date: 15-August-2003
Project Days: 7
Required Start Date: 06-August-2003
(i.e project starts 6th August and is finished by the end of the day
on the 14th)
How can I do this?
TIA,
Dave Ferguson