K
Karl
Hi,
I wonder if anyone can help. Using the workday formula and conditional
formatting I’ve created a Gantt chart in Excel that behaves more or less like
a Project file.
I have one small problem. The WORKDAY function looks like this:
=WORKDAY(D5,F5,C11:E1:F1:G1:H1:I1:J1)-1
The -1 at the end of the formula is there to solve a problem with the Gantt
chart. The WORKDAY function adds the number of days the task lasts (cell F5
in this case) to the start date (D5). So if you enter a duration of 5 days
into F5, you end up with six shaded cells on the Gantt chart; hence the -1.
However, for some reason with the -1 in the formula, a job that the formula
thinks ends on a Monday is shown as ending on a Sunday. So for instance:
Start date (D5) – 02/12/2008 (a Tuesday)
Duration in days (F5) – 4
End date (using above formula) – 07/12/2008 (a Sunday)
So, my question: am I using the WORKDAY function incorrectly? Why doesn’t it
show the job ending the formula minus one working day (Friday 5 December,
which is when the task really does end)?
Is there a better way of getting the WORKDAY function to include the start
date as part of the duration of the task?
And I know I could just enter a duration that’s one day shorter than it
really is, but I want everyone on our project to be able to use this. I don’t
always want to be left wondering if a ten-step project is actually ten days
too long or too short.
Many thanks for any help and advice you can give.
Best regards
Karl
I wonder if anyone can help. Using the workday formula and conditional
formatting I’ve created a Gantt chart in Excel that behaves more or less like
a Project file.
I have one small problem. The WORKDAY function looks like this:
=WORKDAY(D5,F5,C11:E1:F1:G1:H1:I1:J1)-1
The -1 at the end of the formula is there to solve a problem with the Gantt
chart. The WORKDAY function adds the number of days the task lasts (cell F5
in this case) to the start date (D5). So if you enter a duration of 5 days
into F5, you end up with six shaded cells on the Gantt chart; hence the -1.
However, for some reason with the -1 in the formula, a job that the formula
thinks ends on a Monday is shown as ending on a Sunday. So for instance:
Start date (D5) – 02/12/2008 (a Tuesday)
Duration in days (F5) – 4
End date (using above formula) – 07/12/2008 (a Sunday)
So, my question: am I using the WORKDAY function incorrectly? Why doesn’t it
show the job ending the formula minus one working day (Friday 5 December,
which is when the task really does end)?
Is there a better way of getting the WORKDAY function to include the start
date as part of the duration of the task?
And I know I could just enter a duration that’s one day shorter than it
really is, but I want everyone on our project to be able to use this. I don’t
always want to be left wondering if a ten-step project is actually ten days
too long or too short.
Many thanks for any help and advice you can give.
Best regards
Karl