Vacation Commitment doesn't show in "Other Projects" PS 2007

B

boggyboy

In Project Server Timesheet there is an ability to "Plan Administrative
Time". I tried it by entering a week of vacation for a resource. My
expectation was that the vacation time would show in the "Other Projects and
Committments" within a Project Professional Resource Usage view. This was
not the case. Was I incorrect to assume that Vacation committments would
show?
 
D

Dale Howard [MVP]

boggyboy --

It shows, but the line is not listed as Vacation. Instead, it is listed as
My Timesheet. Hope this helps.
 
B

boggyboy

Dale, thanks... I've tried it and don't see anything under "other
committments" in MSProject Pro.
 
D

Dale Howard [MVP]

boggyboy --

In the project, apply the Resource Sheet view. Double-click the name of a
resource that you know has booked vacation and then click the Change Working
Time button. Do you see the My Timesheet entries that indicate vacation as
nonworking time? Let us know what you find out.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top