C
Casey
My staff submitted his vacation schedule through "Notify my manager
time not available for work" in the PWA. The vacation schedule show up
correctly in the Resource Availability view and the Administrative
project that contains the Vacation task.
Somehow, the vacation schedule is offset by several days when seen in
my project openning in Professional. For example, a Xmas vacation now
become like a New Year vacation.
If I open the Administrative project and my project altogether in
Professional, the detail vacation schedule is displayed correctly now.
I checked my project calendar, resource calendar, task calendar and
Project/Options/Calendar settings. They all seem matching correctly.
I am very puzzled by the behavior.
Casey
time not available for work" in the PWA. The vacation schedule show up
correctly in the Resource Availability view and the Administrative
project that contains the Vacation task.
Somehow, the vacation schedule is offset by several days when seen in
my project openning in Professional. For example, a Xmas vacation now
become like a New Year vacation.
If I open the Administrative project and my project altogether in
Professional, the detail vacation schedule is displayed correctly now.
I checked my project calendar, resource calendar, task calendar and
Project/Options/Calendar settings. They all seem matching correctly.
I am very puzzled by the behavior.
Casey