J
Jacques Guertin
Hi all,
Informative stuff here.
Now, let's say that I want to consider resources vacations. What is the
best way around? I though of creating tasks that cannot be leveled, but the
resource pool would wrongly show the same availability as if without
vacations for that period. Example: resource A is off for the next two
weeks. So I create a task assigned to that resource. Problem: I work with
resource pools, i.e. 300%, 400%, etc. availability. So in the resource
histogram, it would still show 400% availability, but with a resource usage
of, say, 300% instead of 200% during that period of time.
Thanks in advance for your clever answers and suggestions.
Jacques G.
Informative stuff here.
Now, let's say that I want to consider resources vacations. What is the
best way around? I though of creating tasks that cannot be leveled, but the
resource pool would wrongly show the same availability as if without
vacations for that period. Example: resource A is off for the next two
weeks. So I create a task assigned to that resource. Problem: I work with
resource pools, i.e. 300%, 400%, etc. availability. So in the resource
histogram, it would still show 400% availability, but with a resource usage
of, say, 300% instead of 200% during that period of time.
Thanks in advance for your clever answers and suggestions.
Jacques G.