Hi,
Is there any way to have the variance table reflect start and finish
variances for tasks which don't have actual start and finish dates?
For example, if a task was supposed to start on 12/1/2005 and it is
12/5/2005, I would like to have to the variance reflect the 4 day start
variance so that I know that technically this task is 4 days behind schedule.
This seems like a good view to have so I can see what my planned schedule
was vs. what is actually currently happening.