I make a project plan in project professional 2007 locally . and make generic
resources with standard rates and assign these generic resources to tasks of
project plan . all is good as per my requirement .
But when I import that project and map that resources with live generic
enterprise resources . after save and publish . the cost and duration is so
different than orignal local project plan.
pls tell me the solution.
and reply me soon.