Hello René,
Open the Task Information dialog box (double click the row of the task) and
go to the Advanced tab:
Task Type = Fixed units
Fixed Duration
Fixed Work
and Effort driven = checked or unchecked
not sure what you're asking .. do you mean why does duration change when you
add resources or change work?
you might like to check out http://tinyurl.com/2xbhc especially lessons 5 &
10 - they were written by Mike Glen and provide a excellent introduction to
how project thinks.
Cheers
JulieD