Variation Duration

Z

zipzip

Please, what is the variable that set Variation of Duration of some task ?
I am using MS Project 2003 Std.
Thank's
Renê
 
G

Gérard Ducouret

Hello René,
Open the Task Information dialog box (double click the row of the task) and
go to the Advanced tab:
Task Type = Fixed units
Fixed Duration
Fixed Work
and Effort driven = checked or unchecked

Nb : Duration x Number of res. units = Work

Gérard Ducouret [Project MVP]
 
J

JulieD

Hi

not sure what you're asking .. do you mean why does duration change when you
add resources or change work?

you might like to check out http://tinyurl.com/2xbhc especially lessons 5 &
10 - they were written by Mike Glen and provide a excellent introduction to
how project thinks.

Cheers
JulieD
 