Varying Weekly Hours for One Task?

  • Thread starter Chris McTiernan
  • Start date
C

Chris McTiernan

I am trying to schedule a software architect to execute a singel task over an 8 week period. The first week, they will dedicate 30 hours, each week thereafter, they will dedicate 10 hours.

How can I track this variable hour allocation within a single task?

Much Obliged,


Chris McTiernan
 
R

Rod Gill

Hi,

Select View, Task Usage or Resource Usage, find the assignment, zoom in or
out until the timescale is weekly then manually edit the work for each week.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
Chris McTiernan said:
I am trying to schedule a software architect to execute a singel task over
an 8 week period. The first week, they will dedicate 30 hours, each week
thereafter, they will dedicate 10 hours.
 