E
Ervin D. Fowlkes
Ok, So I am a brand new project manager at a company that had no
system in place whatsover.
I migrated every task to Project 2007 with PWA and the outlook addin. In our
world I need tasks to be done by a certain date. I manage over 20 projects
with the same 6 developers. I did the insert a project thing into a master
view.
My Question: How do I schedule tasks. I mean, I know how to insert a
task, but what is the mindset?
Am I supposed to use the start date and finish date as the times i need
things done?
I seem to set everything as a "Must finish on" constraint is that right?
If I set the task as ASAP constraint all my tasks start at the project start
Date?
Sorry for being such a newbie.
any and all help greatly appreciated.
system in place whatsover.
I migrated every task to Project 2007 with PWA and the outlook addin. In our
world I need tasks to be done by a certain date. I manage over 20 projects
with the same 6 developers. I did the insert a project thing into a master
view.
My Question: How do I schedule tasks. I mean, I know how to insert a
task, but what is the mindset?
Am I supposed to use the start date and finish date as the times i need
things done?
I seem to set everything as a "Must finish on" constraint is that right?
If I set the task as ASAP constraint all my tasks start at the project start
Date?
Sorry for being such a newbie.
any and all help greatly appreciated.