View assignments by Custom Enterprise Resource Text field

D

Dan Filpus

In our construction business, I have our resources setup in the ERP with a
custom enterprise resource text field I called "Sub-Group." I have all the
resources assigned to a sub-group - Electrical, HVAC, Plumbing, etc. I want
to be able to run a report that pulls up all resources within a certain
sub-group and shows the project, resource, task, & % complete for each
assignment. I've tried to do this in Manage Views under View resource
assignments and Portfolio Analyzer, but I'm striking out. Can I get some
direction? Thanks!!!!!
 
G

Gary L. Chefetz [MVP]

Dan:

There nowhere in the interface using out-of-the-box tools that allows you to
create this exact view. You can build this using SQL reporting services or
Crystal reports against the database.
 