For three project schedules we have items in "View Assignments" that
show incomplete/past due, but in each project it shows 100% complete in
July. I have republished the info (and every other publishing option)
with no improvements.
Also when I look at the data from the tables I can't find where that
info is stored. The dbo_MSP_VIEW_PROJ_ASSN_STD table shows 100%. Any
suggestions on how to fix? And which table?
Thanks for the help
jb
show incomplete/past due, but in each project it shows 100% complete in
July. I have republished the info (and every other publishing option)
with no improvements.
Also when I look at the data from the tables I can't find where that
info is stored. The dbo_MSP_VIEW_PROJ_ASSN_STD table shows 100%. Any
suggestions on how to fix? And which table?