S
Steve Wells
Hi,
Consider this situation.
You have a 10 week task of someone at 50%, giving 25 days of Work.
However, on the first week they work full time and log full days aginst the task.
The total work still shows as being 25 days but the % against the resource name on the Gantt chart shows 100%, presumably just showing the maximum at any time during the task.
Then the next week they do nothing, and then work 50% on the following week.
Total work stays the same and the % against the resource name still shows 100%.
So far that’s fine.
If you go to Resource Center and click View Availability then for week 1 is shows 100%, week 2 it shows 0% and week 3 it shows 50% as expected.
However, for the remaining weeks the person is shown at 100% for the full duration which seems rather misleading.
I would have expected it to be shown at the original 50%.
Can anyone explain this?
It is particularly problematic for background tasks for the year set at say 5%. If the suddenly spend a full day on it then it will show them at 100% for the rest of the year.
Thanks
Steve
Consider this situation.
You have a 10 week task of someone at 50%, giving 25 days of Work.
However, on the first week they work full time and log full days aginst the task.
The total work still shows as being 25 days but the % against the resource name on the Gantt chart shows 100%, presumably just showing the maximum at any time during the task.
Then the next week they do nothing, and then work 50% on the following week.
Total work stays the same and the % against the resource name still shows 100%.
So far that’s fine.
If you go to Resource Center and click View Availability then for week 1 is shows 100%, week 2 it shows 0% and week 3 it shows 50% as expected.
However, for the remaining weeks the person is shown at 100% for the full duration which seems rather misleading.
I would have expected it to be shown at the original 50%.
Can anyone explain this?
It is particularly problematic for background tasks for the year set at say 5%. If the suddenly spend a full day on it then it will show them at 100% for the rest of the year.
Thanks
Steve