View hours worked for specified time frame

M

mbrand

Is it possible to create a view that would show the hours worked on a
project for a specified time frame? The closest I've been able to
think of is filtering based on the start/finish time. But since that
is a wider range than what I want, it does me no good. I'll give a
quick example.

If Project A has a start date of january 1 and end date of of March 31
and has 3 tasks task1, task2, task3. These tasks then have the
following hours worked:

JANUARY FEBRUARY MARCH
TASK1 10h 15h 20h
TASK2 10h 15h 20h
TASK3 10h 15h 20h

I would like to specify a date filter of February. It would then just
show the 3 15 hour tasks, totaling 45 hours.
 
M

mbrand

I would think that if I could get it to show a time sheet view instead
of a gantt chart, it would be possible. Though, as far as I know, I am
unable to do this.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top