R
Rafal_Paczynski
Hi All,
I would like to ask you about set up one view in PWA for team Members.
In order to refine the management of resources we are considering to have
each employee update their assignment in the resource plans for the projects
they are assigned to.
The idea is that the project manager creates a resource plan with the agreed
amount of hours for a particular project and the project team members updates
the resource plan every week i.e. for the next 4 weeks so the plan reflects
reality to a higher degree than today. (The project manager will enter i.e.
50% for the entire span of the project, but the actual workload will most
likely go up and down.)
The question is if it's possible to setup a "my projects" view in the
project center so it will be relative simple for resources to find their
projects and update the resource plans.
I would like to ask you about set up one view in PWA for team Members.
In order to refine the management of resources we are considering to have
each employee update their assignment in the resource plans for the projects
they are assigned to.
The idea is that the project manager creates a resource plan with the agreed
amount of hours for a particular project and the project team members updates
the resource plan every week i.e. for the next 4 weeks so the plan reflects
reality to a higher degree than today. (The project manager will enter i.e.
50% for the entire span of the project, but the actual workload will most
likely go up and down.)
The question is if it's possible to setup a "my projects" view in the
project center so it will be relative simple for resources to find their
projects and update the resource plans.