M
M. Roberts
Hi all,
I've added some custom fields to assign to detail lines
(specifically used to record a "Timesheet Project" code
to which costs for the task will be charged). It's
allowing me to group/report/manipulate based on cost
centres, but only to a point. One of the key reporting
requirements I have is to report on work remaining in
upcoming months, per project, per resource, etc. The
Resource Usage view is great for this, except that my
custom 'Timesheet Project' (of which there may be three
or four in a single *.mpp) fields are task fields, and as
such I can't group by these in the Resource Usage view.
So I'm using the Task Usage view. The limitation here is
that if I have a task which has multiple resources
assigned, and I group by project & resource, I get a
group heading for the combined resource effort, and need
to manually split the time between the resources.
Also, I find it infuriating that the timephased views
have Work, Actual Work (and even Cumulative Work!) but no
Remaining Work (despite Remaining Work being available in
other views...).
I'm using 2002 Professional. Do other versions have
enhancements that solve these issues, or can anyone make
suggestions?
Cheers,
M.
I've added some custom fields to assign to detail lines
(specifically used to record a "Timesheet Project" code
to which costs for the task will be charged). It's
allowing me to group/report/manipulate based on cost
centres, but only to a point. One of the key reporting
requirements I have is to report on work remaining in
upcoming months, per project, per resource, etc. The
Resource Usage view is great for this, except that my
custom 'Timesheet Project' (of which there may be three
or four in a single *.mpp) fields are task fields, and as
such I can't group by these in the Resource Usage view.
So I'm using the Task Usage view. The limitation here is
that if I have a task which has multiple resources
assigned, and I group by project & resource, I get a
group heading for the combined resource effort, and need
to manually split the time between the resources.
Also, I find it infuriating that the timephased views
have Work, Actual Work (and even Cumulative Work!) but no
Remaining Work (despite Remaining Work being available in
other views...).
I'm using 2002 Professional. Do other versions have
enhancements that solve these issues, or can anyone make
suggestions?
Cheers,
M.