Thomas Bräutigam
Hi all,
one question regarding the View Populator Tool for Project Server 2003....or
maybe two questions
Does it prevent sending mails while publishing the choosen projects?
....as I want to avoid annoying mails when publishing projects as an
administrator...
Does it only publish the project schedule data or resource assignments as
well? (Actual Work, Actual Work Protected?)
....as we have "differences" between MSP and PWA in the OLAP Cube...that I
want to eliminate with this action.
Hope for help
Thomas
PS: We're using Project / Server 2003 SP3.
one question regarding the View Populator Tool for Project Server 2003....or
maybe two questions
Does it prevent sending mails while publishing the choosen projects?
....as I want to avoid annoying mails when publishing projects as an
administrator...
Does it only publish the project schedule data or resource assignments as
well? (Actual Work, Actual Work Protected?)
....as we have "differences" between MSP and PWA in the OLAP Cube...that I
want to eliminate with this action.
Hope for help
Thomas
PS: We're using Project / Server 2003 SP3.