View Remaining Work

C

Chuck

Is there some way to view only remaining work in the time
phased section of the Resource Usage View? It would be
beneficial to me to be able to see at a glance the time
phased work remaining to be completed.
 
D

Dale Howard [MVP]

Chuck --

The remaining work for any task is the portion of the Work that extends past
the Actual Work values. For example, on a 40-hour task assignment, a
resource has entered Actual Work values as follows:

M T W Th F
Work 8 8 8 8 8
Act. Work 8 8

The Work values on W, Th, and F represent the timephased remaining work on
the task. If no Actual Work has been entered on a task, then the Work and
Remaining Work are identical. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
G

Guest

I've hunted pretty hard for this, and have yet to find
anything. Maybe someone from MS Development team will
read this and add for next version.
 