D
Dan
OK, let me start by saying that I have been trying to reproduce this for
several days and cannot. Several of our projects, being run by different
PMs, have tasks that show up in PWA > View Resource Assignments but were
removed from the projects several weeks/days ago. In at least one case the
ID has been re-used and two tasks appear in PWA with the same Ent. Proj. ID &
Task ID, assigned to different Ent. Resources.
Any ideas how this could happen?
I have republished the plans and the tasks & assignments numerous times, but
nothing available in the Project Pro UI seems to correct this problem.
Help!
several days and cannot. Several of our projects, being run by different
PMs, have tasks that show up in PWA > View Resource Assignments but were
removed from the projects several weeks/days ago. In at least one case the
ID has been re-used and two tasks appear in PWA with the same Ent. Proj. ID &
Task ID, assigned to different Ent. Resources.
Any ideas how this could happen?
I have republished the plans and the tasks & assignments numerous times, but
nothing available in the Project Pro UI seems to correct this problem.
Help!