G
Griff
I have been testing Project Server 2003 for a while and then recently
installed Project Server 2003 SP1. Since then I have been getting frequent
problems on the view resource assignments page.
Often after selecting one or more resources and clicking apply, the area
where the list should be appears blank (there is actually a very small dot
like a full stop under the links bar). Refreshing the page doesn't solve the
problem but clicking current or all assignments often does.
The number of tasks that should be displayed does not seem to matter,
neither does the number of resources selected. The problem occurs in both the
Timesheet and Gantt Chart formats and also for current and all assignments.
Has anybody got any ideas why this might be happening? Is it a known issue
with SP1? More importantly is there a fix?
installed Project Server 2003 SP1. Since then I have been getting frequent
problems on the view resource assignments page.
Often after selecting one or more resources and clicking apply, the area
where the list should be appears blank (there is actually a very small dot
like a full stop under the links bar). Refreshing the page doesn't solve the
problem but clicking current or all assignments often does.
The number of tasks that should be displayed does not seem to matter,
neither does the number of resources selected. The problem occurs in both the
Timesheet and Gantt Chart formats and also for current and all assignments.
Has anybody got any ideas why this might be happening? Is it a known issue
with SP1? More importantly is there a fix?