Hi !
Normally the "View Resource Availibility" graph in Project Web Access shows
work by project or resource and a line that displays total availibilty.
Ex: displayd work in W 2 is 30 h and availibilty is 35 h
Now the availibility information is gone down to zero hours.
It has happend once before. A huge amount of times were entered into the
work colon of MS project and it recalculatet the task starttime back to
1982. After correcting the amont of work the Web Access Graph showed tha
availibility hours and line again.
Now I can't get it right. I have tried rebuilding The Cube with different
time parameters (from the "Admin page) but no luck. (Default it is set to
use information from start og first project to end og last.)
Is there anyone out there with a goooood idea to solve this problem.
(The availibility info. in MS project is as it should be.)
Using Project Server 2003 aind IE.
Best regards
TT
Normally the "View Resource Availibility" graph in Project Web Access shows
work by project or resource and a line that displays total availibilty.
Ex: displayd work in W 2 is 30 h and availibilty is 35 h
Now the availibility information is gone down to zero hours.
It has happend once before. A huge amount of times were entered into the
work colon of MS project and it recalculatet the task starttime back to
1982. After correcting the amont of work the Web Access Graph showed tha
availibility hours and line again.
Now I can't get it right. I have tried rebuilding The Cube with different
time parameters (from the "Admin page) but no luck. (Default it is set to
use information from start og first project to end og last.)
Is there anyone out there with a goooood idea to solve this problem.
(The availibility info. in MS project is as it should be.)
Using Project Server 2003 aind IE.
Best regards
TT