I have consolidated 3 individual project files into a 4th overall resource
pool file. Pool resource data is set up to take precedance over individual
project data. I want to be able to view only the task assignments associated
with an individual project from within that project file, BUT I want to be
able to see the total commitment of resources from within the resource pool.

So far I have made task assignments from Individual File #1, and they are
viewable from that file as well as the resource pool. I opened up Individual
File #2 and am seeing the task assignments from File #1 previously entered.
I only want to see File #2's task assignments from within File #2. Is this
going to be possible?
 
J

Jan De Messemaeker

Hi

In the Resource Usage View insert a column "Project" and filter thereon
HTH
 