View Timesheet Summary (missing actuals)

T

Thom D

I am currently running MS Office Project Server 2003 with
SP1 applied. At present I have an issue with the 'view
timesheet summary' available when utilising managed
periods.

Some resource actuals (visiable when viewing the
timesheet and view resource assignments) are not visible
in the 'view timesheet summary' area of PWA. It appears
to me that only currently scheduled tasks are being
displayed regardless of the fact that resources have
entered actuals against completed tasks in the current
period.

Can anyone please let me know if this assumption is
correct or if there is any action I may be able to take
to correct this.

Many thanks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top