Is it possible to enable the "View Timesheet Summary" feature without
Protected Actuals, Managed Periods and all the rest of the timesheet
features?

My client has an interest in integration and wants to view the results in
the timesheet summary. The first pass at enabling the timesheet summary
seemed to force us to set managed periods and protected actuals, but they
don't want either.

Any ideas?
 
D

Dale Howard [MVP]

Matthew --

I believe the features are dependent on one another, so that you can't use
one without the others. Sorry.
 
G

Gary L. Chefetz \(MVP\)

Matt:

Can't say for sure without knowing exactly what data you need, but might be
able to cook up something using View Resource Assignments from the Resource
Center.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top