Is there any way that I can generate a table for progress tracking which
shows the following information:
the task name
% of task work completed (the % Work complete field)
% of task work which should have been completed by a specified date (for
example, the status date) according to the baseline schedule.
I've looked at fields such as BCWS and ACWS, but it looks like you have to
enter cost information for these fields to work. I'd like the above progress
information for a project where I haven't entered any costs.
Thank you