M
Martin
I am working with assignment statistics and reporting from a major
project containing 10 subprojects.
I am experiencing the usual problem, that the task's assignments cover
all assignments from all projects on the server. Usually, I would just
save the project offline, shutdown my project pro, start it up again
without logging on to the server, and then only the relevant
assignments would be listed for that project.
However, when saving my masterproject offline, it still just contains
the links to the subprojects.
Now for my questions:
1. Can I somehow save a masterproject including (!) all subprojects in
one file ? (so that I can then do my analysis on that afterwards)
2. Can I somehow limit my assignment view to only containing the
assignments from the current project(s) - AND still enable me to use
the "Analysis of timephased data in Excel" Wizard ?
Thanks !
Martin Kristensen
Senior Project Manager
project containing 10 subprojects.
I am experiencing the usual problem, that the task's assignments cover
all assignments from all projects on the server. Usually, I would just
save the project offline, shutdown my project pro, start it up again
without logging on to the server, and then only the relevant
assignments would be listed for that project.
However, when saving my masterproject offline, it still just contains
the links to the subprojects.
Now for my questions:
1. Can I somehow save a masterproject including (!) all subprojects in
one file ? (so that I can then do my analysis on that afterwards)
2. Can I somehow limit my assignment view to only containing the
assignments from the current project(s) - AND still enable me to use
the "Analysis of timephased data in Excel" Wizard ?
Thanks !
Martin Kristensen
Senior Project Manager