Viewing Committ and Proposed Resources

C

CJM

Wondering if anyone has done any work with viewing Proposed and Committed
resources. As a Resource Manager, using PWA (The only place I can committ
resources) I'd like to view a resource and have a "graphic or a report"
showing me what is committed time, and what is Proposed time on the same
graph or report. At the moment the bar charts show blue but dissapear if you
don't check the "propsed box", the grid below shows a tatalizing option of
"availability" but this just appears to be the overall availability not what
is left. Wondering if anyone else has had this problem, or has a solutions,
or can explain to me how to work project to display this option this
information
 
G

Gary L. Chefetz \(MVP\)

CJM:

Use the Portfolio analyzer to construct this type of view. All the facts and
dimensions are already there, you'll need to create a calculated field to
determine remaining availability as this is not a fact directly tallied in
the system.

--

Gary L. Chefetz, MVP
"We wrote the book on Project Server
http://www.msprojectexperts.com

-
 